Project Name:    REED POINT SCHOOL

Owner:
Architect:
Contractor:
School District #9-9
Schutz-Foss Architect
Fischer Construction



Project Description:
CMS consulted for District 9-9 for design and construction management. Project was 17,500 sf of gymnasium and classroom space for HS/ELEM combination. Project was under-funded due to poor program estimating and required owner management of purchase and installation of all but structural shell. Final project was within 3,500 sf of origanl plan, built and furnished for bond levy amount and completed on time.


Construction Management Services co.

Quality Assurance • Program Management • Construction Management